FR | EN

Carnival Dream

Launched: July 2021
GRT: 128.250 tons

REFERENCES

Carnival Dream

CarnivalDream completed the dry-dock in Marseille at DD 8 between June 24th and July 13th.

CNM performed some main activities as:

  • cleaning
  • blasting of the hull
  • painting with the new forward.

The shipyard has installed 7,2 tons of steel on the ship for repair the forward part, repairing also 3 thrusters and 2 stabilizers.

close

6. News
7. Careers
8. Contacts
Privacy Policy Cookie Policy Legal Disclaimer Company Data

Chantier Naval de Marseille

Terre Plein de Mourepiane - Porte 4 CS 40034
13344 Marseille Cedex 15
Phone: +33 (0) 484 894452
E-mail: info@cndm.eu