Genoa - November 14, 2023

Important works for Saipem completed

Post tags: chantier naval de marseille , Saipem , Castorone , FDS2


In the first half of 2023, San Giorgio del Porto and Chantier Naval de Marseille successfully completed two major dry-docks for Saipem, welcoming the Saipem FDS2 in Genoa and the Castorone in Marseille, once again confirming the excellent synergies and complementarity of the two Genova Industrie Navali Group repair yard

Marseille - Saipem Castorone project in numbers:

Arrival: 17/12/2022
Departure: 09/06/2023
Project duration: 174 days
Days in dry-dock: 156

Major works:

  • Cyclic maintenance works.
  • Tensioners Upgrade.
  • PLET Handling Sytem.
  • New Bilge Keel.
  • Several Upgrades.

 

close

6. News
7. Careers
8. Contacts
Privacy Policy Cookie Policy Legal Disclaimer Company Data

Chantier Naval de Marseille

Terre Plein de Mourepiane - Porte 4 CS 40034
13344 Marseille Cedex 15
Phone: +33 (0) 484 894452
E-mail: info@cndm.eu