We are pleased to share the successful completion of the project related to the FSRU Toscana terminal, the regasification unit of OLT OFFSHORE LNG TOSCANA. This was a complex and articulated operation carried out between Genoa and Marseille, at the San Giorgio del Porto S.p.A. and Chantier Naval de Marseille shipyards, which once again confirmed their role as key partners in the field of ship repair and conversion.
The operation began in April 2024 in Genoa, with an initial phase dedicated to preparing for the replacement of the main turret bearing, dismantling connected structures and equipment (over 85 tons of materials), as well as conducting inspections and maintenance of the cargo tanks and ballast tanks.
In June, the vessel arrived in Marseille, where it was hosted in dry dock for 119 days, during which key structural and maintenance operations were completed, including:
The success of this project once again demonstrates the ability of San Giorgio del Porto and Chantier Naval de Marseille shipyards to manage highly complex operations while ensuring quality and adherence to schedules.
A special thanks to all the teams involved for their commitment, professionalism, and dedication in making this important achievement possible!